Impact
Shared readings after each lift so the team could adjust the lifting operation before securing the jacks and removing the gauges.
Challenge
A controlled jacking operation at Building A required tracking strain in beams connected to Column E4.
STRAAM approach
On July 31, 2018, STRAAM monitored four strain gauges on two beams supporting floors 3–5 and shared readings across four lift stages.
Result
The readings supported adjustments during lifting, before the jacks were secured. The team removed the monitoring gauges at completion.