Impact
Kept findings for 356 and 360 Bowery distinct, giving the construction team useful information about each neighboring building.
Challenge
Adjacent construction called for an assessment at 356 Bowery and monitoring at neighboring 360 Bowery.
STRAAM approach
STRAAM established a baseline at 356 Bowery and monitored 360 Bowery. The final 360 report is monitoring report #13 and lists three accelerometers.
Result
At 356 Bowery, the work identified response concerns and recommended follow-up. At 360 Bowery, monitoring showed no notable tilt trend or high-vibration alerts during the final monitored period.